Solar EPC · Own the Asset

Own your solar plant. Own your energy costs.

Turnkey solar EPC — capex model. Design, supply, installation, and commissioning for commercial and industrial facilities. Minimum 200 kW. PAN India.

100%
Yours from Day 1
18–24%
Typical IRR (Illustrative)
3–5 yrs
Typical payback (Illustrative)
200 kW
Minimum project size
EPC vs RESCO

EPC (Capex) vs RESCO (Zero Capex) — which model is right for you?

Both routes deliver solar at your facility. The difference is who owns the asset — and how you pay for it.

You pay upfront

EPC — Capex model

  • You invest the capital upfront
  • You own the plant from Day 1
  • No ongoing payments to us after commissioning
  • Full savings accrue to you immediately
  • Typical payback: 3–5 years (Illustrative)
  • Typical IRR: 18–24% (Illustrative)
Zero capex

RESCO — Zero capex model

  • We invest — you pay per unit consumed
  • We own the plant through the PPA period
  • 20–30% saving from Day 1, no capital outlay
  • Plant transfers to you at PPA end

IRR and payback figures are illustrative. Actual values depend on your state, DISCOM tariff, and consumption profile.

What we deliver

Every phase. Our responsibility.

From the first shadow analysis to live SCADA monitoring — we own every stage of your project.

01

Engineering & Design

Shadow analysis, structural load study, single-line diagram, and detailed project report. ALMM-listed Tier 1 TOPCon modules. Hot-dip galvanised or aluminium mounting structure specified to your site.

02

Supply & Procurement

We manage the full equipment supply chain — panels, string or central inverters, BOS, mounting, and cabling. No subcontracting of core supply. Equipment ordered directly from manufacturers.

03

Installation & Commissioning

Civil, mechanical, and electrical execution by our team. DISCOM synchronisation, net metering application, and grid connectivity managed end to end — including the DISCOM interface.

04

Monitoring & EPOP Integration

Plant-level SCADA with remote monitoring from Day 1. Generation data feeds directly into the EPOP platform — giving you ongoing procurement optimisation, not just a one-time installation.

Project timeline

12–20 weeks from contract to commissioning.

Timeline varies by state DISCOM and plant size. We manage every step — including the DISCOM interface.

1
Weeks 1–3
Site Assessment & DPR

Shadow analysis, load study, structural survey, and detailed project report. Free of charge, no obligation.

2
Weeks 4–5
Commercial Close

Contract signing, advance payment, equipment order placed with manufacturers.

3
Weeks 5–10
Equipment Procurement

Tier 1 ALMM-listed TOPCon panels, inverters, mounting structure, and BOS components. Lead times managed by us.

4
Weeks 10–14
Civil & Mechanical

Foundation works, mounting structure installation, cable tray routing.

5
Weeks 14–16
Electrical & Commissioning

AC/DC wiring, inverter commissioning, plant SCADA setup, performance baseline established.

Weeks 16–20
DISCOM & Net Metering

DISCOM inspection, net metering application, grid synchronisation. We manage the interface.

Is EPC right for you?

Six criteria. Tick all six and the economics work.

EPC is the right model for facilities that want full ownership and the strongest long-term return. If these criteria fit, a free site assessment will confirm the numbers.

You want to own the solar asset from Day 1

EPC means full ownership from commissioning. The asset sits on your balance sheet, depreciates under Section 32, and generates returns over its 25-year life.

Capital available for a one-time investment

The full project cost is paid by you — typically in milestone tranches. Capex financing through term loans is also available and we can assist with the lender interface.

Peak contracted load ≥ 200 kW

Our minimum EPC project size is 200 kW. This suits facilities with a contracted peak demand of 200 kW or above.

Rooftop or ground space available at your facility

We need clear, unshaded area — rooftop, carport, or open ground. We assess and confirm during the free site visit.

Currently paying ₹6/unit or more to your DISCOM

The economics of solar EPC improve at higher grid tariffs. At ₹6/unit or above, a well-designed plant typically delivers an IRR of 18–24% (illustrative).

Planning to operate from this location for 10+ years

A solar plant has a 25-year operational life. The strongest payback case is for facilities with a long-term commitment to their current site.

Tick all six? A free site assessment confirms your roof area, your DCF model, and the project proposal — before you commit to anything. Get yours →

Frequently asked questions

Common questions about solar EPC.

Get started

Ready to own your energy costs?

Get a free site assessment — we run the numbers on your facility before you commit to anything.

No commitment required. We will contact you within one business day.